How Long Does a CDC or DA Take in NSW?
How long a CDC or DA takes in NSW, what slows both down, and what to do if your CDC is rejected, with Northern Beaches council data.
Deon Du Plessis
11/23/20265 min read
A Complying Development Certificate (CDC) is usually decided in weeks, while a Development Application (DA) usually takes months. Published state data put the average council assessment time for a DA at roughly 70 days across NSW, and at around 100 days for Northern Beaches Council in 2025-26, before any delays for missing information. The state describes fast-tracked CDC approvals as possible in as little as 20 days, and 10 days for its pattern book pathway. What you actually get depends on your property, how complete your application is and who assesses it.
Below is what drives the timeframes, what slows each pathway down, what to do if your CDC is rejected, and how to avoid losing months. It's written from 20 years of designing and documenting renovations for homeowners on Sydney's Northern Beaches.
How long does a CDC take in NSW?
A CDC is issued by council or a private certifier, without a full DA assessment, if the work meets the fixed standards in the planning code. Because the certifier is checking your plans against a checklist, the assessment is much faster than a DA. The state's fast-track figures are 20 days, and 10 days for the pattern book pathway. Many ordinary renovation CDCs take longer than that once the certifier has asked for more information, so allow several weeks and check with your certifier. Not sure whether to use council or a private certifier? See private certifier or council in NSW.
The biggest variable is the application itself. A CDC with complete, accurate drawings, an engineer's details and the right reports moves quickly. One with gaps gets returned. For when a CDC is the right pathway, see our complete CDC guide for the Northern Beaches.
How long does a DA take in NSW?
A DA is assessed by council against its local planning controls, can be notified to neighbours, and may need referrals to other agencies. NSW publishes council performance data, and a few reference points are:
NSW average: the state's Planning page cites an average DA determination time of about 70 days.
Northern Beaches Council: the state league table lists an average assessment time of about 100 days for 2025-26, up from about 86 days in 2024-25. The figures are rolling averages and include simple and complex applications, so a straightforward renovation can be faster and a contentious one slower.
Those numbers measure assessment time. They don't include the time to prepare the application beforehand, or the time your project spends waiting while you respond to council's requests for more information. Check the current council league table for the latest figures, as they change each year.
What slows down a CDC or DA?
Incomplete or inconsistent drawings. Missing dimensions, mismatched plans and elevations, or no existing-conditions drawings are the most common cause of delay. See how to get house plans in NSW if you don't have accurate existing plans.
Missing reports. Structural, BASIX, bushfire, flood, arborist or heritage reports may be needed, depending on the property.
Site constraints. Heritage, bushfire, flood, slope and tree controls can rule out the CDC pathway or add conditions. A 10.7 planning certificate shows which apply.
Neighbour submissions (DA). Objections from neighbours can mean redesign or extra assessment.
Requests for information (DA). Each request can pause the assessment while you respond, which extends the total elapsed time well past the average.
The wrong pathway. Lodging as a CDC something that needs a DA, or the reverse, costs time and fees.
What if your CDC is rejected or refused?
It's more common than people expect, and it usually means something specific can be fixed. In general:
Get the reasons in writing. A certifier can return, decline or refuse an application. Ask exactly which standard wasn't met, or which information was missing.
Work out which kind of problem it is. It may be a gap in the application, a design that doesn't meet a numeric standard such as height, setback or site coverage, or a site that isn't eligible for complying development at all.
Fix and resubmit if it's a design or information issue. Many rejected CDCs are approved after the plans are adjusted to meet the standards.
Lodge a DA if the project can't meet the code. A DA lets council exercise judgement against its planning controls, so a design that fails a fixed standard can still be approved on merit.
Don't assume the DA review process applies. The formal review of determination under section 8.2 of the Act is described by councils in relation to refused DAs, not CDCs, so check with your certifier or a planning adviser what options exist.
If a DA is refused, there are review and appeal rights, with time limits. Get advice quickly and confirm the deadlines.
How can you avoid losing months?
Choose the pathway before you design. Work out whether the project is exempt, a CDC or a DA first. Our DA vs CDC vs exempt development guide explains the differences, and our guide to renovating without council approval shows what needs no approval at all.
Design to meet the code where you can. A small change to a setback or height can move a project from a DA to a CDC and save months.
Lodge a complete application. Drawings, reports and forms that match each other the first time.
Answer requests for information promptly and fully.
Keep the approval's life in mind. Approvals lapse if work doesn't start within the set period, commonly five years, so check the dates on yours.
If you're not sure which pathway applies to your property, an Approval Pathway Report ($495 ex GST) sets out the route for your block, what it needs and a realistic expectation of timing. If you're also weighing a bigger project, see renovate or rebuild.
Frequently asked questions
How long does a CDC take to get approved in NSW?
Usually weeks rather than months. The state describes fast-track approvals in as little as 20 days, and 10 days for its pattern book pathway, but many renovation CDCs take longer, especially if the certifier needs more information. Complete drawings and reports are the biggest factor.
How long does a DA take in NSW?
The state's Planning page cites an average of about 70 days, and the state league table puts Northern Beaches Council's average assessment time at about 100 days in 2025-26. Complex or contested applications take longer, and delays while you respond to council's requests for information are on top of that.
Is a CDC faster than a DA?
Generally yes, because the certifier checks the plans against fixed standards instead of assessing the project on its merits. But a CDC is only available if the property and the design meet the code, so it isn't an option for every project.
What happens if my CDC is rejected?
Ask for the reasons in writing. If the issue is missing information or a design that can be adjusted, fix it and resubmit. If the project can't meet the code or the site isn't eligible, lodge a DA instead.
Can I appeal a rejected CDC?
The formal review of determination process is described by councils for refused DAs, so don't assume it applies to a CDC. Ask your certifier what your options are, and consider advice from a planning lawyer for a contested refusal.
How long is a CDC valid for?
Approvals generally lapse if work doesn't start within a set period, commonly five years, so check the conditions and dates on your certificate. Confirm the period that applies to yours.
Want to know which pathway your project needs?
Whether your project is a CDC, a DA or exempt depends on the property and the design. Book a free 1-hour consult with Beaches Drafting and we'll talk through your property, the likely pathway and how to avoid delays. You can also read about our draftsman services on the Northern Beaches or see our property advice and reports.
Written by Deon Du Plessis, building designer at Beaches Drafting. This page is general information for NSW homeowners as at 2026 and is not legal advice. Timeframes are published averages and guides, change each year and vary by council, certifier and project. Confirm timeframes, fees and rights with your council or an accredited certifier before you rely on them.